Butlins Minehead, January 2021
This project was for Butlins to create a new temporary venue to increase the resort capacity with Covid 19 restrictions in place. Our role was the groundwork contractor, and this is a brief list on the scope of work.
-
Strip the existing soil surface over the approximate area of 10,000 m², lay geotextile membrane and 150mm thick Type 1 to create level area for building to be constructed on, with a tolerance of 50mm.
-
Installation of surface water drainage system, which included the installation of an attenuation tank and vortex flow chamber, connected to the resorts existing drainage system.
-
Installation of foul water drainage system and connecting to the resorts existing drainage system.
-
Installation of utility services such as electric and water to the new venue.
-
Construct 70 metre long and 3 metre tall steel fence with timber hit and miss panelling.
-
Various aspects of surfacing from concrete, tarmac and gravel.