House Foundations

Dulverton, June 2021

We were contracted to install foundations, drainage and constructing up to DPC for a split-level SIP house. Scope of work below.

​

  • Levelling of ground to correct levels

  • Setting out of foundations

  • Concrete foundations

  • Install foul water drainage and sewage treatment plant

  • Install surface water drainage and large soakaway

  • Construction of retaining wall for split level house

  • Setting out of walls on foundations

  • Construct block wall to DPC level

  • Concrete oversite

  • Construct garden retaining walls

  • Form concrete footpaths around outside of house

  • Surface tarmac driveway

  • Level and grade soil around site to suit